Dear Owners and Residents:
Please find below expected work schedule for the week of February 22, 2022:
February 2022
Tuesday, February 22 12th floor Demolition (tile removal)
Tuesday, February 22 5th floor Elevator vestibules tile installation
Wednesday, February 23 6th floor Elevator vestibules tile installation
Thursday, February 24 2nd floor Wall plastering and sanding (1 week)
Thursday, February 24 7th floor Elevator vestibules tile installation
Friday, February, 25 8th floor Elevator vestibules tile installation
Please note that access (via elevators) to the floors where new tiles are set will be restricted from 2:00 p.m. to 8:00 a.m. on the following day. During this time, residents are asked to use the stairs to access these floors. Should you require accommodation and access via elevators during this time, please contact the management office.
Important Notes for your consideration:
Preparing the walls usually generates dust and some noise. This work will take place daily between 9:00 a.m. to 6:00 p.m.
Measures will be taken to reduce dust and cordon off the areas; however, air circulates and some dust should be expected.
Since maintaining a gap for the circulation of fresh air is required by building code, please do not seal your suite door. For the duration of the sanding or demolition period, you may use a damp towel at the bottom of the door to trap some of this air-borne dust. It is highly recommended the residents minimize use of the hallways and work areas.
For safety of residents and the contractors and the building staff, please limit the use of marked work areas, obey instructions provided by the on-site crew, and refrain from disturbing workers with personal inquiries. All inquiries must be communicated via the management office.
Should you have any questions and or concerns, please do not hesitate to contact us.
Kind regards,
Kaveh (Kevin) Oskoui, BSc, RCM, PMP
CMRAO General Licence, Property Manager - Turnberry Court (MTCC805)
management@turnberrycourt.org