Dear Owners and Residents,
We would like to thank everyone for their on-going support and patience during this project.
The crew will continue to work on the interior finishes of the corridors. suite doors, thresholds, and walls.
PROJECT SCHEDULE
April 27 onward Wall paper installation starting from the 2nd floor
Week of April 25 onward Primer Hallway Walls. starting 2nd floor (approx. 2 floors per day)
Week of April 25 onward Painting of hallway ceilings starting at 2nd floor
April 27 - April 29 Office floor demolishing (Phase 1).
Please note that during the office renovations, the office will be closed. Please direct all inquiries via email to management@turnberrycourt.org.
Please continue to be mindful of workers and their equipment. Additional updates will be provided as it becomes available.
Again, we appreciate your understanding and support in this matter, and apologize for any inconvenience this may cause. Should you have any questions, please do not hesitate to contact us.
Kind regards,
Kaveh (Kevin) Oskoui, BSc, RCM, PMP
CMRAO General Licence, Property Manager - Turnberry Court (MTCC805)