Dear Owners and Residents,
We would like to thank everyone for their on-going support and patience during this project.
The construction crew will continue to work on the interior finishes as per following schedule. Other activities may be taking place as needed.
PROJECT SCHEDULE - UPDATE
May 4 - 13 UPDATE Demolition of lobby
On Friday May 13th, work on the elevator vestibule area will begin. During this time, one of the elevators may be out of service to ensure your safety and protect elevators. Please be patient and use the elevators from 2nd floor and P1 when possible. Individuals' recurring accommodation will be assisted by the building staff or on-site construction crew.
May 2 onward Management Office renovations
May 2 onward Installation of new electrical receptacles on all floors
April 27 onward Wall paper installation starting from the 2nd floor
Week of April 25 onward Primer Hallway Walls. starting 2nd floor (approx. 2 floors per day)
Week of April 25 onward Painting of hallway ceilings starting at 2nd floor
Please note that during the lobby renovations, the residents are asked to exercise due caution in work areas, refrain from using the main entrance and use alternative exits. Demolishing the floor will generate dust, noise and vibration in the building. Please plan accordingly. This notice serves as Suite Entry Notice as required by the Condominium Act.
Individuals requiring assistance with access to the building will be accommodated by a building staff. Please do not hesitate to contact the office.
Additional details will be provided as necessary. Once again, we appreciate your understanding and support in this matter, and apologize for any inconvenience this may cause.
Should you have any questions, please do not hesitate to contact us.
Kind regards,